Ingested documents
1,284 files
| Document | Type | Pages | State |
|---|---|---|---|
NMC-PH2 Drawing Set — 100% CD Rev 4 | Drawings | 842 | Indexed |
Project Manual — Divisions 00–48 Issued for Construction | Specifications | 1,960 | Indexed |
Addenda 01–06 Through 12-Feb-2026 | Addenda | 74 | Indexed |
Baseline Schedule Rev. C P6 XER | Schedule | 1,240 | Parsed — 1,240 activities |
Coordinated BIM — Architectural / Structural / MEP r12 | BIM | 3 | Quantities extracted |
RFI Log — Bid Phase 118 RFIs | RFI | 118 | Indexed |
Geotechnical Report Final | Reports | 96 | Indexed |
Site Logistics Plan Rev 3 | Plans | 8 | Indexed |
Owner Contract & Exhibits Executed | Contract | 214 | Indexed |
Check library
19/20 enabled
- 01Scope completeness vs plans & specs
- 02Drawing-to-specification conflicts
- 03BIM/quantity vs schedule activity mismatch
- 04Missing predecessor / successor logic
- 05Impossible or overlapping sequencing
- 06Critical-path vulnerabilities
- 07Excessive or unrealistic float
- 08Duration outliers vs production rates
- 09Long-lead procurement scheduled too late
- 10Inspections, testing & commissioning gaps
- 11Mobilization & site logistics dependencies
- 12Trade handoff / interface gaps
- 13Resource conflicts & crew stacking
- 14Milestone feasibility
- 15Weather & seasonal constraints
- 16Addenda & change orders not reflected
- 17Duplicate or orphan activities
- 18Permit & approval dependencies
- 19Temporary works & closeout coverage
- 20Schedule compression opportunities
Demonstration data for Northstar Medical Center — Phase II: 24 seeded findings, $4.82M modeled exposure and $2.14M modeled opportunity.