Northstar Medical Center — Phase II

$185.40M · Baseline Rev. C — P6 XER · 1,240 activities

Generate Review Package
SeverityCategoryFindingSourceSchedule activity$ impactDaysRecommended actionConf.Status
critical
Negative risk
ProcurementF-001

Air handling units released 14 weeks after required order-by date

Spec 23 73 13 — Custom Air Handling Unitsp. 7, §2.1.BMEP-2210AHU Submittal & Fabrication Release — L3 Mech Rooms$1.24M+14dPull MEP-2210 forward to Nov-2026 and add an early-release procurement activity tied to the design-assist award. Confirm the 38-week lead time in writing with the manufacturer before submission.94%open
critical
Negative risk
Scope completenessF-002

Medical gas rough-in for Level 4 surgical suite absent from schedule

Drawing P-402 — L4 Medical Gas PlanSheet P-402, rev 4PLB-4120L4 Plumbing Rough-In (no med gas sub-activity)$862K+9dAdd med gas rough-in, purity certification and NFPA 99 verification activities under PLB-4120. Confirm inclusion in the estimate before the GMP is locked.91%open
high
Opportunity
Schedule compressionF-003

Podium and tower fit-out can run concurrently after L2 slab pour

Schedule logic scan — Baseline Rev. CActivities INT-3000 → INT-3480INT-3200Podium Interior Fit-Out — Start+$610K-16dRe-link INT-3200 to the L2 slab completion milestone instead of tower fit-out completion, and validate hoist capacity with the logistics plan.86%open
critical
Negative risk
LogicF-004

Elevator installation has no predecessor to shaft completion

Baseline Rev. C — P6 logic exportRelationship table, CNV-5100CNV-5100Elevator Car & Rail Installation — Banks A/B$445K+22dAdd FS predecessor from SHF-4400 (shaft enclosure) with a 5-day lag for embed survey. Re-run the critical path before submission.97%open
high
Negative risk
Spec vs drawingF-005

Curtain wall glazing performance conflicts between spec and elevations

Spec 08 44 13 §2.3 vs Drawing A-231Spec p. 11 / Sheet A-231 keynote 12ENV-2740North Elevation Curtain Wall Glazing$528K+6dIssue a pre-bid RFI to confirm which document governs and price the delta as a clarification in the proposal.89%open
high
Negative risk
CommissioningF-006

Infection control risk assessment testing not scheduled before turnover

Spec 01 35 33 — Infection Control Proceduresp. 4, §3.2CX-6600Commissioning & Turnover — Patient Care Levels$386K+11dInsert ICRA verification and terminal clean activities with a 14-day window ahead of CX-6600 and coordinate with the owner's infection control officer.88%open
high
Opportunity
ProcurementF-007

Switchgear early-release saves 11 days and avoids Q3 escalation

Vendor quotation NS-EL-4471 + Spec 26 13 00Quote §3 price-hold termsELE-3310Main Switchgear Procurement & Delivery+$470K-11dMove ELE-3310 to accept the 90-day price hold and add an on-site storage activity with humidity control per the manufacturer's requirements.83%open
high
Negative risk
ResourcesF-008

Drywall crew stacking exceeds available manpower by 42% in Oct-2027

Resource loading — Baseline Rev. CHistogram, trade code 09-DWINT-4410L2–L5 Drywall Hang & Finish (overlapping)$340K+7dLevel the drywall chain across Sept–Nov or secure a second crew commitment in writing before the schedule is submitted.79%open
critical
Negative risk
PermitsF-009

State health facility plan approval not modeled as a predecessor

Spec 01 41 00 — Regulatory Requirementsp. 2, §1.4PRM-1050CDPHE Plan Review & Approval$415K+30dAdd PRM-1050 as a mandatory predecessor to all patient-care inspection activities and show the statutory review duration explicitly.92%open
medium
Negative risk
DurationF-010

Structural steel erection duration 41% below regional production rate

BIM quantity takeoff + benchmark modelModel NMC-STR-r7, element set 'Frame'STR-2100Structural Steel Erection — Tower Frame$268K+24dRebaseline STR-2100 to 62–68 days or document the second crane and shift assumption that supports the stated rate.81%open
medium
Opportunity
EfficiencyF-011

17 days of idle time between shell completion and interior mobilization

Schedule logic scan — Baseline Rev. CENV-2900 → INT-3000 gap analysisINT-3000Interior Framing Mobilization+$295K-17dRemove the unconstrained gap and re-link INT-3000 directly to ENV-2900 with a 2-day cleanup lag.90%open
medium
Negative risk
AddendaF-012

Addendum 04 imaging suite shielding not reflected in schedule

Addendum 04 — issued 12-Jan-2026p. 3, items 4.7–4.9INT-2050L1 Imaging Suite Partitions$254K+8dAdd shielding installation and magnetic field verification activities, and confirm the addendum is carried in the estimate.87%open
high
Negative risk
InterfaceF-013

No handoff activity between fire alarm and nurse call integration

Spec 28 31 00 §3.6 — Integrated Systems Testp. 9LV-5820Low Voltage Systems Integration$176K+5dAdd a joint integration milestone with both subcontractors as predecessors, scheduled 3 weeks before CX start.76%open
medium
Negative risk
WeatherF-014

Site concrete paving scheduled during Jan–Feb freeze window

Spec 32 13 13 §3.4 + NOAA regional climate dataSpec p. 6SIT-7220Exterior Concrete Paving & Hardscape$148K+12dShift paving to Mar-2028 or price cold-weather protection explicitly and increase the weather allowance in the calendar.84%open
medium
Opportunity
EfficiencyF-015

Modular headwall prefabrication can remove 9 days from patient floors

Spec 10 25 13 §2.2 (substitution permitted)p. 4INT-4620Patient Room Headwall Installation+$385K-9dPrice the prefabricated headwall option and submit as a value-engineering alternate with the schedule.78%open
medium
Negative risk
FloatF-016

Total float of 214 days on 62 activities indicates broken logic

Spec 01 32 16 §1.7 — Float thresholdsp. 3MULTI62 activities across MEP and finishes$210K+0dClose open-ended activities with successors before submission; target maximum total float under 45 days.95%open
low
Negative risk
HygieneF-017

14 orphan activities and 3 duplicate activity IDs

Spec 01 32 16 §1.5 — Schedule qualityp. 2MULTI17 affected activities$46K+0dClean up orphan and duplicate activities before export.99%open
high
Negative risk
BIM vs scheduleF-018

BIM shows 38% more ductwork linear feet than the schedule duration supports

BIM model NMC-MEP-r12 quantity extractElement set 'Duct — Supply/Return'MEP-3900L2–L5 Ductwork Installation$322K+13dReconcile the model quantity against the estimate takeoff and confirm whether shafts are excluded from MEP-3900.74%open
medium
Negative risk
LogisticsF-019

Tower crane dismantle scheduled before roof screen wall steel

Site Logistics Plan rev 3 + Drawing S-601Logistics plan sheet 3GEN-1900Tower Crane Dismantle$165K+6dMove the dismantle after roof steel or explicitly price the mobile crane in general conditions.85%open
medium
Opportunity
EfficiencyF-020

Combining two TAB mobilizations saves $180k and 5 days

Spec 23 05 93 + schedule logic scanp. 3, §3.1CX-6210Test & Balance — Podium+$180K-5dMerge CX-6210 into CX-6300 and confirm zone readiness dates with the CxA.80%open
high
Negative risk
MilestoneF-021

Owner FF&E access milestone is infeasible against finishes completion

Owner Contract Exhibit C — MilestonesExhibit C, Milestone M-7MIL-9100Owner FF&E Access Milestone$298K+26dRebaseline finishes on the top three floors to open the full 45-day window, or negotiate a phased FF&E access agreement before submission.90%open
low
Negative risk
CloseoutF-022

O&M manual and training activities missing from closeout

Spec 01 79 00 — Demonstration and Trainingp. 2CX-6900Project Closeout$68K+4dAdd training and O&M submission activities 30 days ahead of turnover.93%open
low
Opportunity
EfficiencyF-023

Night-shift concrete placement removes 4 days from podium deck cycle

Municipal noise variance NV-2026-114Permit condition 3STR-1720Podium Deck Pours 1–4+$200K-4dConvert deck pours to night placement and confirm concrete supplier night-batch capacity.72%open
medium
Negative risk
Critical pathF-024

Single-point critical path through one electrical room has no mitigation

Critical path analysis — Baseline Rev. CLongest path reportELE-4800L1 Main Electrical Room Energization$264K+12dAdd a temporary power bridge activity and split the energization into two sub-milestones to break the single point of failure.82%open

24 of 24 findings shown. Click any row to open evidence, financial model and workflow actions.

Demonstration data for Northstar Medical Center — Phase II: 24 seeded findings, $4.82M modeled exposure and $2.14M modeled opportunity.