A global engineering firm cut 274 billed schedule hours to about 9.

How a construction management team used IPSES to generate the master schedule, review constructability before bid, audit the contractor's schedules and draft every response, with their own experts signing off on each step.

Client
A $10B world-leading engineering and professional services consulting firm
Project
$193.3M public infrastructure project
Role
Construction management for the public owner
Period
Fall 2026 pilot

Billed schedule hours

As billed274hours
With IPSESabout9hours
Master schedule through monthly audits.
  • 93

    Constructability findings raised before the project went to bid

  • 60 days

    Working days found through resequencing, with no contract periods cut

  • Minutes

    From contract documents to a P6-ready schedule

  • 20 min

    For each monthly audit, instead of about 10 billed hours

Schedule work is budgeted in hours the team rarely has.

  • Building a schedule

    Meant reading every plan sheet and specification, then typing each activity, relationship and duration by hand.

  • Reviewing monthly updates

    Meant tracing every change back through submittals, diaries and look-aheads.

  • The result

    The firm's senior staff spent their time on data entry instead of judgment, and the budget for each task was too small to do a full review.

Pre-bid: master schedule and constructability review

What IPSES did

  • Read 22 source documents: plan sets, specifications, foundation report and agency standards
  • Answered all 171 items of a standard constructability checklist and raised 93 findings and 60 open questions
  • Reconciled plan-sheet quantities against the bid schedule
  • Built a 207-activity CPM schedule that imported straight into P6, then tested 12 resourcing and resequencing options

Business outcome

  • Critical design issues caught before bid, so the designer corrected the plans instead of the owner paying for change orders later
  • 60 working days found through means and methods, each with its justification documented
  • 16 days of logic errors caught and explained before the schedule went out
  1. 22

    source documents read

  2. 171

    checklist items answered

  3. 93 + 60

    findings and open questions raised

  1. 207

    activities in the CPM schedule

  2. P6

    imported straight in, no rework

  3. 12

    resourcing and resequencing options tested

After award: baseline audit, monthly updates and look-aheads

What IPSES did

  • Audited the contractor's baseline against every specification requirement: a key findings summary, a 27-tab compliance workbook and a draft transmittal
  • Reviewed the monthly update against the baseline and project records in an 11-tab workbook
  • Traced the longest path and reconciled the contractor's look-ahead with the current schedule

Business outcome

  • Each monthly audit took about 20 minutes instead of 10 billed hours
  • Early completion from the owner's expedited reviews identified as owner float, protecting it for the owner's use
  • A look-ahead stretching soil nail work from 10 to 17 working days flagged before it reached the next update

Soil nail work in the contractor's look-ahead

Schedule10 working days
Look-ahead17 working days +7
Flagged before it reached the next update.

Changes, delays and draft communications

What IPSES did

  • Tied every finding to the specification section, drawing and schedule activity behind it
  • Identified late submittal days and the contract's daily charge for late schedule submittals
  • Drafted the transmittal and responses to the contractor for the team to review and send

Business outcome

  • Every response starts from the contract, so time and cost discussions are grounded in the record
  • Delays attributed to the right party while there is still time to act
  • Senior staff review and sign off instead of drafting from scratch
  1. Finding

    raised by the review

  2. Specification section

    where the contract requires it

  3. Drawing

    where the plans show it

  4. Schedule activity

    what it affects

Every finding is tied to the section, drawing and activity behind it.
“Unbelievable. The contract time had not yet been identified — that’s my task, as of Thursday afternoon. Apparently you’ve done it in less time than it took me to log in and upload a single project’s documents to my desktop.”
Senior Scheduler, at the client firm

80 hrs

Billable scheduling time saved on one review (about $12,000–20,000)

The bottom line

Schedule work billed at 274 hours took about 9. The hours that used to go to data entry went to judgment: reviewing findings, resolving design issues before bid, and protecting the owner's position.

Client and project details anonymized. Figures are from the client's 2026 pilot.