Schedule work is budgeted in hours the team rarely has.
Building a schedule
Meant reading every plan sheet and specification, then typing each activity, relationship and duration by hand.
Reviewing monthly updates
Meant tracing every change back through submittals, diaries and look-aheads.
The result
The firm's senior staff spent their time on data entry instead of judgment, and the budget for each task was too small to do a full review.
Pre-bid: master schedule and constructability review
What IPSES did
- Read 22 source documents: plan sets, specifications, foundation report and agency standards
- Answered all 171 items of a standard constructability checklist and raised 93 findings and 60 open questions
- Reconciled plan-sheet quantities against the bid schedule
- Built a 207-activity CPM schedule that imported straight into P6, then tested 12 resourcing and resequencing options
Business outcome
- Critical design issues caught before bid, so the designer corrected the plans instead of the owner paying for change orders later
- 60 working days found through means and methods, each with its justification documented
- 16 days of logic errors caught and explained before the schedule went out
22
source documents read
171
checklist items answered
93 + 60
findings and open questions raised
207
activities in the CPM schedule
P6
imported straight in, no rework
12
resourcing and resequencing options tested
After award: baseline audit, monthly updates and look-aheads
What IPSES did
- Audited the contractor's baseline against every specification requirement: a key findings summary, a 27-tab compliance workbook and a draft transmittal
- Reviewed the monthly update against the baseline and project records in an 11-tab workbook
- Traced the longest path and reconciled the contractor's look-ahead with the current schedule
Business outcome
- Each monthly audit took about 20 minutes instead of 10 billed hours
- Early completion from the owner's expedited reviews identified as owner float, protecting it for the owner's use
- A look-ahead stretching soil nail work from 10 to 17 working days flagged before it reached the next update
Soil nail work in the contractor's look-ahead
Changes, delays and draft communications
What IPSES did
- Tied every finding to the specification section, drawing and schedule activity behind it
- Identified late submittal days and the contract's daily charge for late schedule submittals
- Drafted the transmittal and responses to the contractor for the team to review and send
Business outcome
- Every response starts from the contract, so time and cost discussions are grounded in the record
- Delays attributed to the right party while there is still time to act
- Senior staff review and sign off instead of drafting from scratch
Finding
raised by the review
Specification section
where the contract requires it
Drawing
where the plans show it
Schedule activity
what it affects
“Unbelievable. The contract time had not yet been identified — that’s my task, as of Thursday afternoon. Apparently you’ve done it in less time than it took me to log in and upload a single project’s documents to my desktop.”
80 hrs
Billable scheduling time saved on one review (about $12,000–20,000)
The bottom line
Schedule work billed at 274 hours took about 9. The hours that used to go to data entry went to judgment: reviewing findings, resolving design issues before bid, and protecting the owner's position.