A finished review you can open and check.
Sample data for Northstar Medical Center, Phase II. Open any finding to see its evidence, its dollars and its days.
- Contract value
- $185.40M
- Schedule
- Baseline Rev. C, P6 XER
- Activities
- 1,240
| Finding | Category | Source | Schedule activity | Impact | Days | Confidence | Status |
|---|---|---|---|---|---|---|---|
| Procurement | Spec 23 73 13 — Custom Air Handling Unitsp. 7, §2.1.B | MEP-2210AHU Submittal & Fabrication Release — L3 Mech Rooms | −$1.24M | +14 d | 94% | Open | |
| Scope completeness | Drawing P-402 — L4 Medical Gas PlanSheet P-402, rev 4 | PLB-4120L4 Plumbing Rough-In (no med gas sub-activity) | −$862K | +9 d | 91% | Open | |
| Schedule compression | Schedule logic scan — Baseline Rev. CActivities INT-3000 → INT-3480 | INT-3200Podium Interior Fit-Out — Start | +$610K | −-16 d | 86% | Open | |
| Logic | Baseline Rev. C — P6 logic exportRelationship table, CNV-5100 | CNV-5100Elevator Car & Rail Installation — Banks A/B | −$445K | +22 d | 97% | Open | |
| Spec vs drawing | Spec 08 44 13 §2.3 vs Drawing A-231Spec p. 11 / Sheet A-231 keynote 12 | ENV-2740North Elevation Curtain Wall Glazing | −$528K | +6 d | 89% | Open | |
| Commissioning | Spec 01 35 33 — Infection Control Proceduresp. 4, §3.2 | CX-6600Commissioning & Turnover — Patient Care Levels | −$386K | +11 d | 88% | Open | |
| Procurement | Vendor quotation NS-EL-4471 + Spec 26 13 00Quote §3 price-hold terms | ELE-3310Main Switchgear Procurement & Delivery | +$470K | −-11 d | 83% | Open | |
| Resources | Resource loading — Baseline Rev. CHistogram, trade code 09-DW | INT-4410L2–L5 Drywall Hang & Finish (overlapping) | −$340K | +7 d | 79% | Open | |
| Permits | Spec 01 41 00 — Regulatory Requirementsp. 2, §1.4 | PRM-1050CDPHE Plan Review & Approval | −$415K | +30 d | 92% | Open | |
| Duration | BIM quantity takeoff + benchmark modelModel NMC-STR-r7, element set 'Frame' | STR-2100Structural Steel Erection — Tower Frame | −$268K | +24 d | 81% | Open | |
| Efficiency | Schedule logic scan — Baseline Rev. CENV-2900 → INT-3000 gap analysis | INT-3000Interior Framing Mobilization | +$295K | −-17 d | 90% | Open | |
| Addenda | Addendum 04 — issued 12-Jan-2026p. 3, items 4.7–4.9 | INT-2050L1 Imaging Suite Partitions | −$254K | +8 d | 87% | Open | |
| Interface | Spec 28 31 00 §3.6 — Integrated Systems Testp. 9 | LV-5820Low Voltage Systems Integration | −$176K | +5 d | 76% | Open | |
| Weather | Spec 32 13 13 §3.4 + NOAA regional climate dataSpec p. 6 | SIT-7220Exterior Concrete Paving & Hardscape | −$148K | +12 d | 84% | Open | |
| Efficiency | Spec 10 25 13 §2.2 (substitution permitted)p. 4 | INT-4620Patient Room Headwall Installation | +$385K | −-9 d | 78% | Open | |
| Float | Spec 01 32 16 §1.7 — Float thresholdsp. 3 | MULTI62 activities across MEP and finishes | −$210K | +0 d | 95% | Open | |
| Hygiene | Spec 01 32 16 §1.5 — Schedule qualityp. 2 | MULTI17 affected activities | −$46K | +0 d | 99% | Open | |
| BIM vs schedule | BIM model NMC-MEP-r12 quantity extractElement set 'Duct — Supply/Return' | MEP-3900L2–L5 Ductwork Installation | −$322K | +13 d | 74% | Open | |
| Logistics | Site Logistics Plan rev 3 + Drawing S-601Logistics plan sheet 3 | GEN-1900Tower Crane Dismantle | −$165K | +6 d | 85% | Open | |
| Efficiency | Spec 23 05 93 + schedule logic scanp. 3, §3.1 | CX-6210Test & Balance — Podium | +$180K | −-5 d | 80% | Open | |
| Milestone | Owner Contract Exhibit C — MilestonesExhibit C, Milestone M-7 | MIL-9100Owner FF&E Access Milestone | −$298K | +26 d | 90% | Open | |
| Closeout | Spec 01 79 00 — Demonstration and Trainingp. 2 | CX-6900Project Closeout | −$68K | +4 d | 93% | Open | |
| Efficiency | Municipal noise variance NV-2026-114Permit condition 3 | STR-1720Podium Deck Pours 1–4 | +$200K | −-4 d | 72% | Open | |
| Critical path | Critical path analysis — Baseline Rev. CLongest path report | ELE-4800L1 Main Electrical Room Energization | −$264K | +12 d | 82% | Open |
24 of 24 findings shown. Open a finding to see its evidence, financial model and recommended action.
Other example projects
West Ridge Data Center — Hall 3
Meridian Digital
$96.2M
640 activities
Analysis queued, health 71
Harborline Transit Extension
Regional Transit Authority
$243.0M
No schedule
Draft — awaiting schedule upload
Cedar Mills Water Treatment Upgrade
City of Cedar Mills
$61.8M
512 activities
Analysis completed, health 88
Example data for Northstar Medical Center — Phase II: 24 findings, $4.82M modeled exposure and $2.14M modeled opportunity.